DuPage County’s plans to replace the aging Fullersburg Bridge on York Road in Oak Brook have been slowed while they are reviewed by the agency charged with protecting historically significant sites in the state.
The Illinois Historic Preservation Agency could force DuPage to repair rather than replace the structure, which highway officials rate the worst among county-maintained bridges.
At the same time, the county is paying an extra $34,000 to a Chicago engineering firm to prepare alternate drawings and specifications in an effort to appease area business owners who want one lane of the bridge to be kept open during construction.
Rebuilding or replacing a bridge is usually among the most difficult of construction projects.
But it gets trickier when the bridge is included on the National Register of Historic Places, as the Fullersburg Bridge is because of its proximity to the landmark Graue Mill. And it gets even trickier when it’s on a busy road like York, linking Oak Brook and Hinsdale, two of the county’s wealthier communities.
The mill, built in 1852 on Salt Creek, is the only working grist mill in the Midwest and one of the few authenticated Underground Railroad stations in Illinois.
County highway officials are trying to balance a host of sometimes-competing interests-those of nearby business owners who fear economic hardship if the bridge is closed for repairs for several months; those of preservationists who worry about disturbing the ambience of Graue Mill; and those of the thousands of motorists who use York Road.
But the first concern is safety, said Charles Tokarski, the county’s chief highway engineer.
“The driving force for the project is the condition of the bridge,” Tokarski said. “That’s the reason we feel this is urgently needed. We did have sections of the deck fall into the river.”
Tokarski said the state rates bridges on a scale of 1 to 100-with 100 being the best-for such factors as safety of design and condition of roadway.
“This bridge rates about a 4,” he said. “Our next worst is a 57. This is far and away the worst bridge on the county road system.”
The county’s proposal for a $2.5 million bridge replacement and road improvement project has been controversial since it was announced last spring. Hinsdale residents voiced concerns about plans to roughly double the width of the bridge, adding a left-turn lane and walkways on both sides for pedestrians and bicyclists. Oak Brook officials favor the bike paths.
The county says the existing bridge, two lanes with a narrow shoulder, is beyond repair. Tokarski also noted that the brick side walls were not designed to stop a car from crashing through and tumbling into Salt Creek.
In a letter last month to the state historic preservation agency, the county’s consulting engineers recommended replacement for safety reasons and because it would be cheaper in the long run.
Envirodyne Engineers estimated that it would cost about $425,000 to extend the life of the bridge by 25 years. Replacing the bridge would cost about $974,000, but a new bridge could be expected to last 50 years.
The analysis was done without determining the condition of the bridge supports, and Tokarski said there are some questions about the adequacy of the foundation if the bridge were rehabbed.
The county’s plans require approval from the Illinois Historic Preservation Agency because the bridge is considered part of the Graue Mill site. The agency already has determined that the project would have an adverse impact on the site, which means DuPage must now convince the agency that there are no suitable alternatives.
County officials contend that the bridge itself is not historic, only old.
But David Blanchette, a spokesman for the state agency, said the bridge, built in the early 1920s, “has a number of unique architectural features.”
“We believe it has some historic value over and above its location,” Blanchette said. “The bridge and the mill are being considered by us as one whole.”
State historic preservation officials had asked the county to consider rehabbing the existing bridge and building a separate bridge for pedestrians and bicyclists to the east.
Tokarski said the county considered relocating the bridge but dropped the idea because it would have cost an additional $700,000 to $1.5 million. Part of the additional cost would have resulted from the need to acquire land from the Forest Preserve District and private property owners.
How to handle the construction is a separate issue.
Prospective bidders will be asked to quote costs based on shutting down the bridge for the project and separately on keeping a lane open during construction. Members of the County Board’s Transportation Committee reluctantly recommended spending extra money for additional plans in hopes of convincing business owners that the increase in cost and time would not justify keeping one lane open.
“Businesses definitely feel they want one lane open,” said County Board member Patricia Bellock (R-Hinsdale). “This is the main road that everyone here uses to get north.”